| Planning Application Number: | RB2025/1468 |
| Site Address: | land at Long Lane Whiston |
| Description: | Erection of a new 400kV Gas Insulated Switchgear (GIS) substation including gantries, internal access roads, a GIS building, parking, drainage, emergency diesel generator, lighting and CCTV, permanent access road from Long Lane, earthworks, landscaping and biodiversity enhancement, and fencing and the permanent realignment of Whiston Footpath 10 |
| Status: | Dec |
| Decision Level/Committee: | Committee |
| Decision: | GRANTED CONDITIONALLY |
|---|---|
| Date Received: | 11 November 2025 |
| Date Valid: | 11 November 2025 |
| Date Consultees Notified: | 17 November 2025 |
| Date Neighbours Notified: | 17 November 2025 |
| Date Recommendation Made: | 08 July 2026 |
| Committee Date: | 16 July 2026 |
| Deferred Date: | 18 August 2026 |
| Decision Date: | 19 August 2026 |
| Sent Date: | 19 August 2026 |
| Consultation Period Begins: | 17 November 2025 |
| Consultation Period Ends: | 18 December 2025 |