Rotherham Metropolitan Borough Council Online Planning - Full Details
| Planning Application Number: | RB2026/0877 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Site Address: | land at Long Lane Brinsworth 9999 | ||||||||||||
| Description: | Section 37 consent for permanent and temporary diversion works to National Grid 400kV overhead transmission line (Brinsworth–Chesterfield route) | ||||||||||||
| Application Status: | Valid | ||||||||||||
| Date Valid: | 24 June 2026 | ||||||||||||
| Decision: | |||||||||||||
| Decision Date: | |||||||||||||
| Sent Date: | |||||||||||||
| Decision Level/Committee: | Proposed to be Delegated | ||||||||||||
| Appeal: | No | ||||||||||||
| Case Officer and Phone No.: | Andrew West 01709 254753 | ||||||||||||
| Applicant Name & Address: | National Grid Electricity Transmission plc National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6D | ||||||||||||
| Agent Name & Address: | |||||||||||||
| Agent Phone No: | |||||||||||||
| Ward: | Sitwell Ward | ||||||||||||
| Parish: | Whiston | ||||||||||||
| Area Team: | |||||||||||||
| Listed Building Grade: | |||||||||||||
| Departure from Local Plan: | No | ||||||||||||
| Major Development: | No | ||||||||||||
| Date Received: | 24 June 2026 | ||||||||||||
| Statutory Period End Date: | 05 August 2026 | ||||||||||||
| Recommendation Date: | |||||||||||||
| Committee Date: | |||||||||||||
| Deferred: | |||||||||||||
| Deferred Date: | |||||||||||||
| Temporary Expiry Date: | |||||||||||||
| Site Notice Date: | |||||||||||||
| Advert Date: | |||||||||||||
| Consultation Period Begins: | 25 June 2026 | ||||||||||||
| Consultation Period Ends: | 30 July 2026 | ||||||||||||
| Constraints: |
| ||||||||||||
| Consultees: |
| ||||||||||||
| Neighbours: | |||||||||||||
| Amendments: | |||||||||||||

Application Received on 24 June 2026
Public Consultation starts 25 June 2026 and ends 30 July 2026
No decision