Rotherham Metropolitan Borough Council Online Planning - Full Details
Application Status
Application Received on 24 December 2021
Application Registered on 06 January 2022
Processed
Public Consultation ended on 28 January 2022
Application decided 03 August 2022
Planning Application Number: | RB2022/0002 | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Site Address: | West Melton Electricity Substation Elsecar Road Brampton Bierlow 9999 | ||||||||||||||||
Description: | Extension to Electricity Substation including raising of land levels with installation of new plant and equipment and fencing along with a new temporary access | ||||||||||||||||
Application Status: | Dec | ||||||||||||||||
Date Valid: | 24 December 2021 | ||||||||||||||||
Decision: | GRANTED CONDITIONALLY | ||||||||||||||||
Decision Date: | 03 August 2022 | ||||||||||||||||
Sent Date: | 08 August 2022 | ||||||||||||||||
Decision Level/Committee: | Delegated (Part 2A) | ||||||||||||||||
Appeal: | No | ||||||||||||||||
Case Officer and Phone No.: | Anthony Lowe 01709 823840 | ||||||||||||||||
Applicant Name & Address: | Rockhaus Limited | ||||||||||||||||
Agent Name & Address: | The Abbey Group Cambs Limited Nene Lodge Funthams Lane Whittlesey PE7 2PB |
||||||||||||||||
Agent Phone No: | 07880030078 | ||||||||||||||||
Ward: | Hoober Ward | ||||||||||||||||
Parish: | Brampton Bierlow | ||||||||||||||||
Area Team: | North | ||||||||||||||||
Listed Building Grade: | |||||||||||||||||
Departure from Local Plan: | No | ||||||||||||||||
Major Development: | No | ||||||||||||||||
Date Received: | 24 December 2021 | ||||||||||||||||
Statutory Period End Date: | 10 August 2022 | ||||||||||||||||
Recommendation Date: | 03 August 2022 | ||||||||||||||||
Committee Date: | |||||||||||||||||
Deferred: | |||||||||||||||||
Deferred Date: | 03 August 2022 | ||||||||||||||||
Temporary Expiry Date: | |||||||||||||||||
Site Notice Date: | |||||||||||||||||
Advert Date: | |||||||||||||||||
Consultation Period Begins: | 07 January 2022 | ||||||||||||||||
Consultation Period Ends: | 28 January 2022 | ||||||||||||||||
Constraints: |
| ||||||||||||||||
Consultees: |
| ||||||||||||||||
Neighbours: | |||||||||||||||||
Amendments: | |||||||||||||||||
View MapView Plans & DocumentsView Decision Notice SummaryProgress Summary