| Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby permitted shall relate to the area shown outlined in red on the location plan (received on 09.09.2025) and the development shall only take place in accordance with the submitted details and specifications as shown on the approved amended plans (as set out below)
Drawing number:-
• MS/81/25 – 01 (amended plan received on 03.10.2025)
Reason
To define the permission and for the avoidance of doubt.
03
The materials to be used in the construction of the external surfaces of the development hereby permitted shall be in accordance with the details provided in the submitted application form and email correspondence dated 10.09.2025. The development shall thereafter be carried out in accordance with these details.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity.
Informative
01
You have indicated on the application form, by completion of Certificate A on the certificate of ownership form, that nobody except the applicant was the owner of any part of the land to which the application relates. As such, no part of the building, including foundations or guttering, should project over the boundary of your property.
Positive and Proactive Statement
During the determination of the application, the Local Planning Authority worked with the applicant to consider what amendments were necessary to make the scheme acceptable. The applicant agreed to amend the scheme so that it was in accordance with the principles of the National Planning Policy Framework.
|