| Conditions / Reason for Refusal: |
Based on the evidence submitted it is considered that the flood alleviation works are permitted development under Part 13 Class C of the General Permitted Development Order
First Schedule
Proposed Flood Alleviation Works as shown on the following drawings:
17_174_550-PF-A2G-02-DR-C-020_001-P02 Rev P02
17_174_550-PF-A2G-02-DR-C-020_002-P01 Rev P01
17_174_550-PF-A2G-02-DR-C-060_001-P04 Rev P04
17_174_550-PF-A2G-01-DR-C-060_002-P02 Rev P02
17_174_550-PF-A2G-02-DR-C-060_003-P03 Rev P03
17_174_550-PF-A2G-02-DR-C-060_004-P02 Rev P02
17_174_550-PF-A2G-02-DR-C-060_005-P02 Rev P02
17_174_550-PF-A2G-01-DR-C-060_006-P01 Rev P01
17_174_550-PF-A2G-01-DR-C-060_007-P01 Rev P01
Second Schedule
At land flanked by the River Don, at Rotherham Cut, south of Stonerow Way and west of Eastwood (Sir Frank Price) Lock, S65, 3SH, Rotherham
|