| Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans (as set out below)
(Drawing numbers location plan 22002_01, proposed second floor 22002_07, elevations 22002_08, 22002_09, street scene 22002_10)(received 24 March 2025)
Reason
To define the permission and for the avoidance of doubt.
03
The new rooflight windows along the western elevation facing 1 and 7a Church Street shall be obscurely glazed and fitted with glass to a minimum industry standard of Level 3 obscured glazing and be non-openable, unless the part(s) of the window(s) which can be opened are more than 1.7 metres above the floor of the room in which the window is installed. The window(s) shall be permanently retained in that condition thereafter.
Reason
In the interests of the amenities of the occupiers of adjoining properties.
04
The materials to be used in the construction of the external surfaces of the development hereby permitted shall be in accordance with the details provided in the submitted application form/shown on drawing nos. Elevations 22002_08, 22002_09. The development shall thereafter be carried out in accordance with these details.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity and in accordance with Core Strategy Policy CS28 Sustainable Design.
05
The Cycle Storage provision as shown on drawing (ref proposed second floor 22002_07) shall be implemented prior to the occupation of the first flat.
Reason
In order to promote sustainable transport choices.
Construction Environmental Management Plan (CEMP)
06
Prior to the development commencing a Construction Environmental Management Plan (CEMP) shall be submitted to and agreed in writing with the Local Planning Authority. The plan shall describe in detail the actions that will be taken to minimise adverse impacts on occupiers of nearby properties and shall provide information in respect of the following matters:
Program and Phasing Details
- Site layout
- Expected duration of demolition and construction work phases
Site Management
- Contact details of site manager
- Complaints procedure
- Roles and responsibilities
- Details of public liaison meetings (including details of the frequency of meetings and of those to be invited to the meetings).
Routes for Construction Traffic
- Routes to be used to and from the site along the road network within the Rotherham Borough.
- Proposed access/egress points onto the site.
- One way systems
- Haul routes (on-site and delivery)
NOTE: Where temporary access is required during the construction phase, these should benefit from separate planning permission if not approved under the host permission. Appropriate S278/S184 Agreements (as appropriate) must be gained from the Highways Authority before any works commence on site.
Site Access, Storage and Movement of Materials
- Delivery access point details
- Location details of storage areas
- Delivery times of materials and plant
- Location of on site parking and turning provision
Dust, Debris and Mud
- Screening and hoarding
- Preventative measures
- Details of soil and its movement and temporary storage during construction
- Dust suppression measures - General and machinery
- Wheel wash facilities (including details of source of water)
- Road sweeping facilities
- Covering of dusty stockpiles
- Vehicles carrying dusty loads
- Dust monitoring
- Boundary checks
- Monitoring of weather including wind speed and direction, dry conditions etc
NOTE: Regards shall be had to the guidance detailed in Institute of Air Quality Management- Guidance of the assessment of dust from demolition and construction 2014. In addition, measures shall be taken to minimise mud on nearby public roads, such that road sweepers are only required on these roads in exceptional/emergency circumstances.
Noise and Vibration Control
- Silencing of vehicles, plant and machinery.
- Mitigation measures for noisy operations
- Operational hours (to include site opening hours, operational hours of workers, and delivery of goods hours).
- One way systems
- Vehicle reverse alarms (white noise reversing alarms should be used as opposed to bleeper alarms, particularly where close to residential properties)
- Leaflet drops to noise sensitive premises
NOTE: Regards shall be had to the guidance detailed in BS5228 2009: Noise and Vibration Control on Construction Sites.
Artificial Lighting
- Hours of operation of the lighting
- Location and specification of all of the luminaires
- Level of maintained average horizontal illuminance for the areas that needs to be illuminated
- Predicted vertical illuminance that will be caused by the proposed lighting when measured at windows of any properties in the vicinity.
- Measures that will be taken to minimise or eliminate glare and stray light arising from the use of the lighting that is caused beyond the boundary of the site.
NOTE: Regards shall be had to the guidance detailed in the Institute of Lighting Professionals - Guidance Note 01/21 Reduction of Obtrusive Light.
Waste Management
- Waste storage
- Waste collection
- Recycling
- Waste removal
Constructional techniques in respect of the Overhead Power Lines of the adjacent electricity cable.
The agreed CEMP shall be adhered to throughout the construction of the development.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with part 15 of the NPPF and Supplementary Planning Document No.2 Air Quality & Emissions.
Informative
The applicant is reminded that only the creation of the new second floor element of the application including external changes to the alterations to the roof and new windows have been considered on this application. The earlier Prior Notification application RB2023/0024 (and has been subsequently updated under RB2024/0341) considered the principle of the ground and first floor residential conversion and is live until September 2027.
Positive and Proactive Statement
Whilst the applicant did not enter into any formal pre application discussions with the Local Planning Authority, the proposals were in accordance with the principles of the National Planning Policy Framework and following clarifications, did not require any alterations or modification.
|