| Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications as shown on the approved plans (as set out below)
(Drawing numbers location plan, block plan and site plan, elevations and floor plans JBA.4023.002)(received 06/02/25).
Reason
To define the permission and for the avoidance of doubt.
03
Notwithstanding the submitted details, the external materials shall be in accordance with the details provided in the submitted application form. The development shall thereafter be carried out in accordance with the approved details.
Reason
To ensure that appropriate materials are used in the construction of the development in the interests of visual amenity and in accordance with Local Plan Policies and the NPPF.
04
Should the shipping containers hereby approved no longer be required on site, they shall be removed from the site and the land restored to its original grass condition.
Reason
In the interest of visual amenity.
Positive and Proactive Statement
Whilst the applicant did not enter into any pre application discussions with the Local Planning Authority, the proposals were in accordance with the principles of the National Planning Policy Framework and did not require any alterations or modification.
|