| Conditions / Reason for Refusal: |
Conditions
The Development Management Procedure Order 2015 requires that planning authorities provide written reasons in the decision notice for imposing planning conditions that require particular matters to be approved before development can start. Conditions numbered 02 & 03 of this permission require matters to be approved before development works begin; however, in this instance the conditions are justified because:
1. In the interests of the expedient determination of the application it was considered to be appropriate to reserve certain matters of detail for approval by planning condition rather than unnecessarily extending the application determination process to allow these matters of detail to be addressed pre-determination.
2. The details required under condition numbers 02 & 03 are fundamental to the acceptability of the development and the nature of the further information required to satisfy these conditions is such that it would be inappropriate to allow the development to proceed until the necessary approvals have been secured.
01
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans (as set out below)
(Amended Phase 1 Infrastructure Plan n2073 401 Rev F)
(Amended Phase 1 Infrastructure Plan n2703 402)
Reason
To define the permission and for the avoidance of doubt.
02
Prior to the commencement of construction of the road, (excluding ground preparation works) road sections, constructional and drainage details shall be submitted to and approved by the Local Planning Authority.
Reason
No details having been submitted they are reserved for approval.
03
No work or storage on the site shall commence until all the trees/shrubs to be retained have been protected by the erection of a strong durable 2 metre high barrier fence in accordance with BS 5837:2012 Trees in Relation to Design, Demolition and Construction - Recommendations This shall be positioned in accordance with the submitted Arboricultural Method Statement dated February 2024. The protective fencing shall be properly maintained and shall not be removed without the written approval of the Local Planning Authority until the development is completed. There shall be no alterations in ground levels, fires, use of plant, storage, mixing or stockpiling of materials within the fenced areas.
Reason
To ensure the trees/shrubs are protected during the construction of the development in the interests of amenity.
Informative(s)
01
You should note that the Council’s Neighbourhood Enforcement have a legal duty to investigate any complaints about noise or dust which may arise during the construction phase. If a statutory nuisance is found to exist they must serve an Abatement Notice under the Environmental Protection Act 1990. Failure to comply with the requirements of an Abatement Notice may result in a fine of up to £20,000 upon conviction in the Magistrates' Court. It is therefore recommended that you give serious consideration to reducing general disturbance by minimising dust and preventing mud, dust and other materials being deposited on the highway.
02
Nature conservation protection under UK and EU legislation is irrespective of the planning system and the applicant should therefore ensure that any activity undertaken, regardless of the need for any planning consent, complies with the appropriate wildlife legislation. If any protected species are found on the site then work should halt immediately and an appropriately qualified ecologist should be consulted. For definitive information primary legislative sources should be consulted.
Furthermore, vegetation removal should be undertaken outside of the bird breeding season, March to September inclusive. If any clearance work is to be carried out within this period, a nest search by a suitably qualified ecologist should be undertaken immediately preceding the works. If any active nests are present, work which may cause destruction of nests or, disturbance to the resident birds must cease until the young have fledged.
POSITIVE AND PROACTIVE STATEMENT
The applicant and the Local Planning Authority engaged in pre application discussions to consider the development before the submission of the planning application. The application was submitted on the basis of these discussions, or was amended to accord with them. It was considered to be in accordance with the principles of the National Planning Policy Framework.
|