| Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved location plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans
Drawing numbers 2024-52-2A received 30 May 2024
Reason
To define the permission and for the avoidance of doubt.
03
No development, including any demolition and groundworks, shall take place until the applicant, or their agent or successor in title, has submitted a Written Scheme of
Investigation (WSI) that sets out a strategy for archaeological investigation and this has been approved in writing by the Local Planning Authority. The WSI shall include:
• The programme and method of site investigation and recording.
• The requirement to seek preservation in situ of identified features of importance.
• The programme for post-investigation assessment.
• The provision to be made for analysis and reporting.
• The provision to be made for publication and dissemination of the results.
• The provision to be made for deposition of the archive created.
• Nomination of a competent person/persons or organisation to undertake the works.
• The timetable for completion of all site investigation and post-investigation works.
Thereafter the development shall only take place in accordance with the approved WSI and the development shall not be brought into use until the Local Planning Authority has confirmed in writing that the requirements of the WSI have been fulfilled or alternative timescales agreed.
Reason
To ensure that any archaeological remains present, whether buried or part of a standing building, are investigated and a proper understanding of their nature, date, extent and significance gained, before those remains are damaged or destroyed and that knowledge gained is then disseminated.
04
The materials to be used in the construction of the external surfaces of the development hereby permitted shall be in accordance with the details provided in the submitted application form/shown on drawing no 2024-52-2A. The development shall thereafter be carried out in accordance with these details.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity.
05
Details of the facilities for the storage of horse manure/stable waste and its means of disposal from the site, shall be submitted to and approved in writing by the Local Planning Authority before the use of the stables is commenced. The facilities shall be provided and thereafter maintained in accordance with the approved details.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with RMBC Policy SP52 and part 15 of the NPPF.
06
No manure or waste materials shall be burned upon the land within the application site.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with RMBC Policy SP52 and part 15 of the NPPF.
07
The stables hereby approved shall be for private use only, and shall not be used for business purposes i.e. livery, riding school etc.
Reason
In the interests of highway safety.
08
Before the development is brought into use, that part of the site to be used by vehicles shall be constructed with either;
a/ a permeable surface and associated water retention/collection drainage, or;
b/ an impermeable surface with water collected and taken to a separately constructed water retention/discharge system within the site.
The area shall thereafter be maintained in a working condition.
Reason
To ensure that surface water can adequately be drained and to encourage drivers to make use of the parking spaces and to ensure that the use of the land for this purpose will not give rise to the deposit of mud and other extraneous material on the public highway in the interests of the adequate drainage of the site and road safety.
09
All ecological measures and/or works shall be carried out in accordance with the
details contained in Section 5, Biodiversity Impact Assessment by Armstrong Ecology Ltd (December 2024).
Reason
In order to protect local wildlife and increase biodiversity on the site.
The Development Management Procedure Order 2015 requires that planning authorities provide written reasons in the decision notice for imposing planning conditions that require particular matters to be approved before development can start. Conditions numbered 03 of this permission require matters to be approved before development works begin; however, in this instance the conditions are justified because:
i. In the interests of the expedient determination of the application it was considered to be appropriate to reserve certain matters of detail for approval by planning condition rather than unnecessarily extending the application determination process to allow these matters of detail to be addressed pre-determination.
ii. The details required under condition numbers 03 are fundamental to the acceptability of the development and the nature of the further information required to satisfy these conditions is such that it would be inappropriate to allow the development to proceed until the necessary approvals have been secured.’
Informative(s)
01
This development is not subject to the statutory Biodiversity Gain Plan condition because of the declaration on the application form that the development was exempt (because the planning application was submitted before the statutory requirement for minor applications).
POSITIVE AND PROACTIVE STATEMENT
During the determination of the application, the Local Planning Authority worked with the applicant to consider what amendments were necessary to make the scheme acceptable. The applicant agreed to amend the scheme so that it was in accordance with the principles of the National Planning Policy Framework.
|