Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration
of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning
Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red
on the approved site plan and the development shall only take place in
accordance with the submitted details and specifications as shown on the
approved plans (as set out below)
(Amended Proposed Elevations, Floor Plans & Site Plan JBA.3548.501.B)
Reason
To define the permission and for the avoidance of doubt.
03
The site shall not be used for dog exercise and training other than between
the hours of 09:00 – 17:00hrs Mondays to Fridays and 09:00 – 13:00hrs on
Saturdays. No operations shall take place on Sundays.
Reason
In the interest of neighbouring amenity.
04
The approved dog training and exercise ground hereby approved shall be
used by Thornberry Animal Sanctuary only or successor of. There shall be no
more than a maximum of 3 No. dogs on site at any one time.
Reason
The site is not suitable for general public use.
05
A Close boarded fencing shall be installed on site as shown in Figure 5.1 of
the Noise Impact Assessment report undertaken by KP Acoustics dated 25
May 2023 (Ref: report 26547.NIA.01 Rev A). The fencing shall have a
minimum height of 2.2m and a minimum surface mass of 10kg/m2 with no
holes or gaps. The fencing shall be regularly inspected and maintained
throughout the duration of the planning consent.
Reason
To safeguard the amenities of the occupiers of the proposed development in
accordance with RMBC Policy SP52 and parts 12 and 15 of the NPPF
06
Landscaping of the site as shown on the approved plan (drawing no.
JBA.3548.501.B) shall be carried out during the first available planting season
after commencement of the development. Any plants or trees which within a
period of 5 years from completion of planting die, are removed or damaged, or
that fail to thrive shall be replaced within the next planting season.
Assessment of requirements for replacement planting shall be carried out on
an annual basis in September of each year and any defective work or
materials discovered shall be rectified before 31st December of that year.
Reason
To ensure that there is a well laid out scheme of healthy trees and shrubs in
the interests of amenity.
07
The hardstanding to the access fronting Moor Land North shall be repaired in
agreement with the Local Planning Authority prior to the use hereby approved
being implemented.
Reason
In the in the interest of highway safety.
POSITIVE AND PROACTIVE STATEMENT
During the determination of the application, the Local Planning Authority
worked with the applicant to consider what amendments were necessary to
make the scheme acceptable. The applicant agreed to amend the scheme so
that it was in accordance with the principles of the National Planning Policy
Framework.
|