| Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications as shown on the approved plans (as set out below)
Drawing Nos:
• 1:100, 1:500, 1:2500 scale plan - Site/Location/Floor Plans
• 1:100 scale plan - Proposed elevations; and
• 1:100 scale plan – Sections & Floor levels.
Reason
To define the permission and for the avoidance of doubt.
03
The development hereby granted shall not be begun until details of the foul & surface water and all related works necessary to drain the site have been submitted to and approved by the Local Planning Authority. These works shall be carried out concurrently with the development and the drainage system shall be operating to the satisfaction of the Local Planning Authority prior to the occupation of the development.
Reason
To ensure that the site is connected to suitable drainage systems and to ensure that full details thereof are approved by the Local Planning Authority before any works begin and in accordance with Policy CS25 of the Local Plan.
04
Unless otherwise approved in writing by the Local Planning Authority, there shall be no piped discharge of surface water from the development prior to the completion of the approved surface water drainage works and no buildings shall be occupied or brought into use prior to completion of the approved foul drainage works.
Reason
To ensure that no foul or surface water discharge take place until proper provision has been made for their disposal in accordance with CS24 of the Local Plan
05
Before the development is brought into use, that part of the site to be used by vehicles shall be constructed with either;
a/ a permeable surface and associated water retention/collection drainage,
or;
b/ an impermeable surface with water collected and taken to a separately constructed water retention/discharge system within the site.
The area shall thereafter be maintained in a working condition.
Reason
To ensure that surface water can adequately be drained and that mud and other extraneous material is not deposited on the public highway and that each dwelling can be reached conveniently from the footway in the interests of the adequate drainage of the site, road safety and residential amenity.
06
Before the development is first brought into use the car parking and turning areas as shown on the Site/Location/Floor Plans shall be provided, marked out and thereafter maintained for car parking and turning.
Reason
To ensure the provision of satisfactory garage/parking/turning space and avoid the necessity for the parking of vehicles on the highway in the interests of road safety.
07
No above ground development shall take place above ground level until details of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted or samples of the materials have been left on site, and the details/samples have been approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details/samples.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity and in accordance with Core Strategy Policy CS28 ‘Sustainable Design’.
08
Before the development is brought into use, a Landscape scheme, showing location and types of landscape treatment, shall be submitted for approval by the Local Planning Authority. The Landscape scheme should be prepared in accordance with RMBC Landscape Design Guide (April 2014) and shall be implemented in the next available planting season and maintained to ensure healthy establishment. Any plants dying, removed or destroyed within five years of planting shall be replaced the following planting season.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity and in accordance with Core Strategy Policies CS21 ‘Landscape,’ and CS28 ‘Sustainable Design’.
09
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification) no extensions to the new dwelling hereby permitted shall be undertaken and no windows/dormer windows or rooflights, other than those expressly authorised by this permission, shall be constructed, without the prior written approval of the Local Planning Authority.
Reason
In the interests of the amenities of the occupiers of adjoining properties.
10
In the event that during development works unexpected significant contamination is encountered at any stage of the process, the local planning authority shall be notified in writing immediately. Any requirements for remedial works shall be submitted to and approved in writing by the Local Authority. Works thereafter shall be carried out in accordance with an approved Method 2 Statement. This is to ensure the development will be suitable for use and that identified contamination will not present significant risks to human health or the environment.
Reason
To ensure the safe occupation of the site in accordance with Policy SP54 of the Rotherham Local Plan and paragraph numbers 189 and 190 of the National Planning Policy Framework.
11
If subsoil’s / topsoil’s are required to be imported to site for garden or soft landscaping areas, then these soils will need to be tested at a rate and frequency to be agreed with the Local Authority to ensure they are free from contamination. The results of testing will need to be presented in the format of a Validation Report.
Reason
To ensure the safe occupation of the site in accordance with Policy SP54 of the Rotherham Local Plan and paragraph numbers 189 and 190 of the National Planning Policy Framework.
14
Following completion of any remedial/ground preparation works a Validation Report should be forwarded to the Local Authority for review and comment. The validation report shall include details of the remediation works and quality assurance certificates to show that the works have been carried out in full accordance with the approved methodology. Details of any post-remedial sampling and analysis to show the site has reached the required clean-up criteria shall be included in the validation report together with the necessary documentation detailing what waste materials have been removed from the site. The site shall not be brought into use until such time as all validation data has been approved by the Local Authority.
Reason
To ensure the safe occupation of the site in accordance with Policy SP54 of the Rotherham Local Plan and paragraph numbers 189 and 190 of the National Planning Policy Framework.
Informative(s)
01
INF 11A Control of working practices during construction phase (Close to residential)
You should note that the Council’s Neighbourhood Enforcement have a legal duty to investigate any complaints about noise or dust which may arise during the construction phase. If a statutory nuisance is found to exist they must serve an Abatement Notice under the Environmental Protection Act 1990. Failure to comply with the requirements of an Abatement Notice may result in a fine of up to £20,000 upon conviction in Rotherham Magistrates' Court. It is therefore recommended that you give serious consideration to reducing general disturbance by restricting the hours that operations and deliveries take place, minimising dust and preventing mud, dust and other materials being deposited on the highway.
02
The applicant is advised that access for fire appliances should be in accordance with Building Regulations Approved Document B volume 1 part B5 section 11.
03
Drainage Informatives
In order to discharge Condition 3 and 4 (drainage details), the applicant is advised that they would be expected to submit information including but not limited to the following:
Surface water drainage plans should include the following:
? Rainwater pipes, gullies and drainage channels including cover levels.
? Inspection chambers, manholes and silt traps including cover and invert levels.
? Pipe sizes, pipe materials, gradients and flow directions.
? Soakaways, including size and material.
? Typical inspection chamber / soakaway / silt trap and SW attenuation details.
? Site ground levels and finished floor levels.
Surface Water Discharge From Brownfield Site:
There should be no increase in surface water discharge from the site to existing sewers / watercourses. On site surface water attenuation will therefore be required if drained areas to existing sewers / watercourses are to be increased.
A 30% net reduction to existing peak discharge (up to a 1/100 yr storm + 40% CC) will be required if the site is being re-developed. A full justification will be required where the development cannot achieve the 30% betterment on the existing run-off rate.
On Site Surface Water Management:
The site is required to accommodate rainfall volumes up to 1 in 100 year return period (plus climate change) whilst ensuring no flooding to buildings or adjacent land.
The applicant will need to provide details and calculations including any below ground storage, overflow paths (flood routes), surface detention and infiltration areas etc. to demonstrate how the 100 year + 40% CC rainfall volumes will be controlled and accommodated.
Where cellular storage is proposed and is within areas where it may be susceptible to damage by excavation by other utility contractors, warning signage should be provided to inform of its presence. Cellular storage and infiltration systems should not be positioned within highway.
Guidance on flood pathways can be found in BS EN 752.
Positive and Proactive Statement
Whilst the applicant did not enter into any pre application discussions with the Local Planning Authority, the proposals were in accordance with the principles of the National Planning Policy Framework and did not require any alterations or modification
|