| Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved location plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans
Reason
To define the permission and for the avoidance of doubt.
03
The materials to be used in the construction of the external surfaces of the development hereby permitted shall be in accordance with the details provided in the submitted application form/shown on drawing no 416/4. The development shall thereafter be carried out in accordance with these details.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity.
04
The following activities must not be carried out under any circumstances.
a. No fires to be lit on site within 10 metres of the nearest point of the canopy of any retained tree/hedgerow on or adjacent to the proposal site.
b. No equipment, signage, fencing etc shall be attached to or be supported by any retained tree on or adjacent to the application site,
c. No temporary vehicle access within designated root protection areas
d. No mixing of cement or dispensing of fuels or chemicals within 10 metres of any retained tree/hedgerow on or adjacent to the application site.
e. No soak- aways to be routed within the root protection areas of any retained tree/hedgerow on or adjacent to the application site.
f. No mechanical excavations within the root protection areas of any retained tree/hedgerow on or adjacent to the application site.
g. No topsoil, building materials or other to be stored within the root protection areas of any retained tree/hedgerow on or adjacent to the application site.
Reason
To ensure appropriate tree protection in the interests of protecting the visual amenity of the area, contributing to the quality and character of Rotherham’s environment, air quality and adapting to and mitigating climate change in accordance with Rotherham’s Core Strategy Policies CS3: Location of New Development, CS19: Green Infrastructure, CS20 Biodiversity and Geodiversity, Policy CS21 Landscape, Policy CS28 Sustainable Design.
Positive and Proactive Statement
Whilst the applicant did not enter into any pre application discussions with the Local Planning Authority, the proposals were in accordance with the principles of the National Planning Policy Framework and did not require any alterations or modification.
|