| Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans (as set out below)
(Drawing numbers location plan and site plan, floorplans and elevations 003 Rev A received 10.08.22).
Reason
To define the permission and for the avoidance of doubt.
03
The use hereby approved shall be for a skin care clinic only (and no other use within Use Class E).
Reason
To define the permission and as this development site is within a predominantly residential area that is not considered suitable for more general medical or retail uses within class E.
Hours of Use
04
The use shall only be operational during the following hours (this includes deliveries along with any customers or visiting members of the public).
10:00 – 20:00hrs Mondays, Tuesdays and Thursdays,
10:00 – 14:00hrs on Saturdays.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with
RMBC Policy SP52 and part 15 of the NPPF.
Fixed Plant
05
No noise generating plant including air conditioning or extraction plant shall be installed in any part of the development until full and precise details have been submitted to and approved in writing by the Local Planning Authority. The details shall include a BS4142:2014 +A1:2019 noise assessment and 1/3 octave frequency analysis with appropriate corrections for acoustic features and shall detail any mitigation measures, physical or operational to achieve no more than 3dB(A)
below the prevailing background levels, outside the boundary of the nearest noise sensitive property during the quietest measured period.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with
RMBC Policy SP52 and parts 12 & 15 of the NPPF. hours
Positive and Proactive Statement
Whilst the applicant did not enter into any pre application discussions with the Local Planning Authority, the proposals were in accordance with the principles of the National Planning Policy Framework and following clarifications did not require any alterations or modification.
|