| Conditions / Reason for Refusal: |
Conditions
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans (as set out below)
(Proposed Elevations 21_55_06G & 21_55_07G) (Received 10 January 2023)
(Proposed Roof Plan 21_55_05B) (Received 28 January 2022)
(Proposed Basement Plan 21_55_02B) (Received 28 January 2022)
(Proposed Ground Floor Plan 21_55_03D) (Received 28 January 2022)
(Amended Site Plan 21_55_01D)
(Topography Plan 21_55_27A)
(Amended First Floor Plans 21_55_04D) (Received 16/02/2022)
(Amended Sewer Standoff Plan 21_55_28)
Reason
To define the permission and for the avoidance of doubt.
03
No above ground development shall take place until details of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted and the details/samples have been approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details/samples.
Reason
To ensure that appropriate materials are used in the construction of the development in the interests of visual amenity and in accordance with Local Plan policies.
04
Before the development is brought into use, that part of the site to be used by vehicles shall be constructed with either;
a/ a permeable surface and associated water retention/collection drainage, or;
b/ an impermeable surface with water collected and taken to a separately
constructed water retention/discharge system within the site.
The area shall thereafter be maintained in a working condition.
Reason
To ensure that surface water can adequately be drained and that mud and other extraneous material is not deposited on the public highway and that each dwelling can be reached conveniently from the footway in the interests of the adequate drainage of the site, road safety and residential amenity and in accordance with Local Plan Policy.
05
A plan indicating the positions, design, materials and type of boundary treatment to be erected shall be submitted to and approved in writing by the Local Planning Authority. The approved boundary treatment details shall be completed before the development is brought into use.
Reason
In order to ensure a satisfactory appearance in the interests of visual and neighbouring amenity.
06
Prior to the occupation of the dwelling, details of one vehicle charging point shall be submitted to and approved by the Local Planning Authority. The dwelling shall not be occupied until the charging point has been provided, and shall thereafter be retained.
Reason
In the interests of sustainable development and air quality.
07
Prior to the occupation of the dwelling, a detailed landscape scheme shall be submitted to, and approved in writing by, the Local Planning Authority. The landscape scheme shall be prepared to a minimum scale of 1:200 and shall clearly identify through supplementary drawings where necessary:
-The extent of existing planting, including those trees or areas of vegetation that are to be retained, and those that it is proposed to remove.
-The extent of any changes to existing ground levels, where these are proposed.
-Any constraints in the form of existing or proposed site services, or visibility requirements.
-Areas of structural and ornamental planting that are to be carried out.
-A planting plan and schedule detailing the proposed species, siting, quality and size specification, and planting distances.
-A written specification for ground preparation and soft landscape works.
-The programme for implementation.
-Written details of the responsibility for maintenance and a schedule of operations, including replacement planting, that will be carried out for a period of 5 years after completion of the planting scheme.
The scheme shall thereafter be implemented in accordance with the approved landscape scheme within a timescale agreed, in writing, by the Local Planning Authority.
Reason
To ensure that there is a well laid out scheme of healthy trees and shrubs in the interests of amenity and ecology.
08
Above ground development shall not begin until details of the proposed means of disposal of foul and surface water, including details of any off-site work and on site attenuation of surface water flows, have been submitted to and approved by the Local Planning Authority and the development shall not be brought into use until such approved details are implemented.
Reason
To ensure that the development can be properly drained in accordance with the Local plan and the NPPF.
09
No piped discharge of surface water from the application site shall take place until works to provide a satisfactory outfall, other than the existing local public sewerage, for surface water have been completed in accordance with details submitted to and approved by the Local Planning Authority.
Reason
To ensure that the site is properly drained and in order to prevent overloading, surface water is not discharged to the public sewer network.
10
No building or other obstruction including landscape features shall be located over or within 3 metres either side of the centre line of the 300mm and 375mm public sewer i.e. a protected strip width of 6 metres, that crosses the site. Furthermore, no construction works in the relevant area(s) of the site shall commence until measures to protect the public sewerage infrastructure that is laid within the site boundary have been implemented in full accordance with details that have been submitted to and approved by the Local Planning Authority. The details shall include but not be exclusive to the means of ensuring that access to the pipe for the purposes of repair and maintenance by the statutory undertaker shall be retained at all times. If the required standoff or protection measures are to be achieved via diversion or closure of the sewer, the developer shall submit evidence to the Local Planning Authority that the diversion or closure has been agreed with the relevant statutory undertaker and that, prior to construction in the affected area, the approved works have been undertaken.
Reason
In the interest of public health and maintaining the public sewer network
11
If during development works unexpected significant contamination is encountered, works shall cease immediately and the Local Planning Authority shall be notified in writing immediately. Any requirements for remedial works shall be submitted to and approved in writing by the Local Planning Authority. Works thereafter shall be carried out in accordance with an approved Method Statement.
Reason
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property
and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
12
If subsoil/topsoil is required to be imported to site for garden or soft landscaping areas, then these soils will need to be tested at a rate and frequency to be agreed with the Local Planning Authority to ensure they are free from contamination. The results of testing will need to be presented in the format of a Validation Report.
Reason
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property
and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
13
Details of boundary treatment or bollards to prevent vehicles access to the rear yard of 23 Worksop Road, Swallownest shall be submitted to and approved by the Local Planning Authority. The approved details shall be implemented before the development is brought into use and thereafter retained during the lifetime of the development.
Reason
In the interest of highway safety.
|