| Conditions / Reason for Refusal: |
01
The works to which this consent relates shall be commenced before the expiration of three years from the date of this consent.
Reason
In order to comply with the requirements of Section 18 of the Planning (Listed
Buildings and Conservation Areas) Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the
submitted details and specifications as shown on the approved plans (as set out below)
• Location Plan Drawing No. 435249/010/00 dated October 2019
• Existing North Wing Elevations with Detailing Drawing No. 435249/003/00 dated October 2019
• Existing East Wing Elevations with Detailing Drawing No. 435249/004/00 dated October 2019
• Existing Roof Plan Detailing Drawing No. 435249/005/00 dated October 2019
• Existing Roof Plan Image Drawing No. 435249/008/00 dated October 2019
• Design and Access Statement dated November 2019
• Reason
To define the permission and for the avoidance of doubt.
Informative
Wildlife Legislation - Bats
Nature conservation protection under UK and EU legislation is irrespective of the planning system and the applicant should therefore ensure that any activity undertaken, regardless of the need for any planning consent, complies with the appropriate wildlife legislation. If any protected species are found on the site then work should halt immediately and an appropriately qualified ecologist should be consulted. For definitive information primary legislative sources should be consulted.
Positive and Proactive Statement
The applicant and the Local Planning Authority engaged in pre application discussions to consider the development before the submission of the planning application. The application was submitted on the basis of these discussions, or was amended to accord with them. It was considered to be in accordance with the principles of the National Planning Policy Framework.
|