| Conditions / Reason for Refusal: |
01
a. Application for approval of reserved matters must be made within three years of the date of this permission.
b. The development hereby approved must be begun not later than whichever is the later of the following dates:
i) The expiration of five years from the date of this permission; OR
ii) The expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
Before the commencement of the development, details of the layout, appearance, access and landscaping of the site shall be submitted to and approved by the Local Planning Authority and the development shall be carried out in accordance with the approved details.
Reason
No details of the matters referred to having been submitted, they are reserved for the subsequent approval of the Local Planning Authority.
03
The detailed elevational drawings and internal layout plans to be submitted in accordance with the requirements of this permission shall indicate a dwelling at a maximum two storey height.
Reason
To minimise potential dominance to the neighbouring residential properties along with the western boundary, facing Victoria Road West.
04
Before the development is brought into use, that part of the site to be used by vehicles shall be properly constructed with either
a/ a permeable surface and associated water retention/collection drainage, or
b/ an impermeable surface with water collected and taken to a separately constructed water retention / discharge system within the site.
All to the satisfaction of the Local Planning Authority and shall thereafter be maintained in a working condition.
Reason
To ensure that surface water can adequately be drained and to encourage drivers to make use of the parking spaces and to ensure that the use of the land for this purpose will not give rise to the deposit of mud and other extraneous material on the public highway in the interests of the adequate drainage of the site and road safety.
05
All gates shall be hung so as not to encroach into the highway when open or being opened.
Reason
In the interests of highway safety.
06
Car park provision is in accordance with the Councils parking standards.
Reason
To ensure that adequate car parking is provided for the proposed development.
Yorkshire Water
07
The site shall be developed with separate systems of drainage for foul and surface water on and off site. The separate systems should extend to the points of discharge to be agreed.
Reason
In the interest of satisfactory and sustainable drainage.
08
No development shall take place until details of the proposed means of disposal of foul water drainage for the whole site including details of any balancing works and off-site works have been submitted to and approved by the Local Planning Authority.
Reason
To ensure that no foul water discharges take place until proper provision has been made for their disposal.
09
There shall be no piped discharge of surface water from the development prior to the completion of surface water drainage works, details of which will have been submitted to and approved by the Local Planning Authority. If discharge to public sewer is proposed, the information shall include, but not be exclusive to:-
a) evidence to demonstrate that surface water disposal via infiltration or
watercourse are not reasonably practical;
b) evidence of existing positive drainage to public sewer and the current points of
connection; and
c) the means of restricting the discharge to public sewer to the existing rate less a
minimum 30% reduction, based on the existing peak discharge rate during a 1 in 1 year storm event, to allow for climate change.
Reason
To ensure that no surface water discharges take place until proper provision has been made for its disposal and in the interest of sustainable drainage).
10
Before the development is brought into use, a Landscape scheme, showing location and types of landscape treatment, shall be submitted for approval by the Local Planning Authority. The Landscape scheme should be prepared in accordance with RMBC Landscape Design Guide (April 2014) and shall be implemented in the next available planting season and maintained to ensure healthy establishment. Any plants dying, removed or destroyed within five years of planting shall be replaced the following planting season.
Reason
To ensure the tree works are carried out in a manner which will maintain the health and appearance of the trees in the interests of the visual amenities of the area and in accordance with the Local Plan.
Environmental Health – Construction Phase
11
Except in case of emergency, no operations shall take place on site other than between the hours of 0800 to 1800 hours Monday to Friday and between 0900 to 1300 hours on Saturdays. There shall be no working on Sundays or Public Holidays. The Planning Authority shall be notified at the earliest opportunity of the occurrence of any such emergency and a schedule of essential work shall be provided.
Reason
In order to reduce the potential impact on the surroundings in the interests of the residential amenity of the area and in accordance with the Local Plan.
12
All machinery and vehicles employed on the site shall be fitted with effective silencers of a type appropriate to their specification and at all times the noise emitted by vehicles, plant, machinery or otherwise arising from on-site activities, shall be minimised in accordance with the guidance provided in British Standard 5228 Code of Practice; 'Noise Control on Construction and Open Sites', and Minerals Planning Guidance Note 11 (1993) 'The Control of Noise at Surface Mineral Workings'.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with RMBC Policy SP52 and the NPPF.
13
At all times during the carrying out of operations authorised or required under this permission, best practicable means shall be employed to minimise dust. Such measures may include water bowsers, sprayers whether mobile or fixed, or similar equipment. At such times when due to site conditions the prevention of dust nuisance by these means is considered by the Planning Authority in consultations with the site operator to be impracticable, then movements of soils and overburden shall be temporarily curtailed until such times as the site/weather conditions improve such as to permit a resumption.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with RMBC Policy SP52 and the NPPF.
14
Effective steps shall be taken by the operator to prevent the deposition of mud, dust and other materials on the adjoining public highway caused by vehicles visiting and leaving the site. Any accidental deposition of dust, slurry, mud or any other material from the site, on the public highway shall be removed immediately by the developer.
Reason
To safeguard the amenities of the occupiers of nearby properties in accordance with RMBC Policy SP52 and the NPPF.
POSITIVE AND PROACTIVE STATEMENT
During the determination of the application, the Local Planning Authority worked with the applicant to consider what amendments were necessary to make the scheme acceptable. The applicant agreed to amend the scheme so that it was in accordance with the principles of the National Planning Policy Framework.
|