| Conditions / Reason for Refusal: |
01
The permission hereby granted shall relate to the area shown outlined in red on the approved location plan and the development shall only take place in accordance with the submitted details and specifications as shown on the approved plans (as set out below)
Drawing number:-
• PROPOSED ELEVATIONS, Drawing Number 154461, Version 4 Page 5
• SIGN A – ILLUMINATED FLEX SIGN, Drawing Number 154461, Version 4 Page 6
• SIGN G – LOADING BAY SIGN, Drawing Number 154461, Version 6 Page 12, amended plan received on 30.04.2026
• BLOCK & SITE LOCATION PLAN – SIGNAGE, Drawing Number ICE700-ROTHERHAM-SP01 REV. A, amended plan received on 05.05.2026
Reason
To define the permission and for the avoidance of doubt.
Informative
01
Most signs that require illumination are for those premises that will be open at night to indicate that they are open. It is recommended that after closure they are turned off, this may in some cases be because there are residential properties nearby and there is no need for them to be on once the shop is closed. For other locations it is good practice to ensure they are turned off after closure or on a timer until later at night if they close at 5pm and would like them on for advertising purposes though are not required to be on 24 hours a day.
For information and general guidance relating to the control of light pollution please refer to the Institution of Lighting Engineers website at:
http://www.ile.org.uk/index.php?page=pollution
02
It is recognised that construction/renovation works are currently being carried out to the rear of the site. The applicant is reminded that whilst permitted development rights exist for extensions and alterations of commercial business or service premises, works that do not meet permitted development requirements require full planning permission.
Positive and Proactive Statement
Whilst the applicant did not enter into any pre application discussions with the Local Planning Authority, the proposals were in accordance with the principles of the National Planning Policy Framework and did not require any alterations or modification.
|