Conditions / Reason for Refusal: |
The Development Management Procedure Order 2015 requires that planning authorities provide written reasons in the decision notice for imposing planning conditions that require particular matters to be approved before development can start. Conditions numbered 5, 6, 8, 13 and 14 of this permission require matters to be approved before development works begin; however, in this instance the conditions are justified because:
i. In the interests of the expedient determination of the application it was considered to be appropriate to reserve certain matters of detail for approval by planning condition rather than unnecessarily extending the application determination process to allow these matters of detail to be addressed pre-determination.
ii. The details required under condition numbers 5, 6, 8, 13 and 14 are fundamental to the acceptability of the development and the nature of the further information required to satisfy these conditions is such that it would be inappropriate to allow the development to proceed until the necessary approvals have been secured.’
General
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved location plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans
Location Plan at scale 1:1250 dated 28-Oct-2024
23024-LE-00-ZZ-DR-D-0800 rev P04 – Proposed Levels Sheet 1
23024-LE-00-ZZ-DR-D-0801 rev P03 – Proposed Levels Sheet 2
23024-LE-00-ZZ-DR-D-0803 rev P03 – General Arrangement
23024-LE-00-ZZ-DR-D-0802 rev P03 – Site Clearance
Reason
To define the permission and for the avoidance of doubt.
Materials
03
Notwithstanding the details submitted as part of this application, prior to construction works commencing above ground level, details of the materials to be used in the construction of the external surfaces of the development hereby permitted shall be submitted to the Local Planning Authority or samples of the materials shall be left on site, and the development shall thereafter be carried out in accordance with the approved details/samples.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity.
04
Notwithstanding the details submitted as part of the application, prior to construction works commencing above ground level details of the finish to the retaining wall, boundary treatment and wall capping shall be submitted to and approved in writing by the Local Planning Authority.
Reason
To ensure it is of an appropriate design and material for the immediate area and to allow for surveillance of the adjacent waterway.
General Amenity
05
Prior to any works commencing on site a Construction Environment Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The CEMP shall describe in detail the actions that will be taken to minimise adverse impacts on occupiers of nearby properties by effectively controlling:
• Noise & vibration arising from all construction and demolition related activities - Contractors and site staff are expected to use the best practical means to minimise noise on site. Regard shall be had to the guidance detailed in BS5228 2009: ‘Noise and Vibration Control on Construction Sites’.
• Dust arising from all construction and demolition related activities - Contractors and site staff are expected to use the best practical means to minimise dust on site. Regard shall be had to the guidance detailed in Institute of Air Quality Management- Guidance of the assessment of dust from demolition and construction 2014.
• Artificial lighting used in connection with all construction related activities and security of the construction site - Contractors and site staff are expected to use the best practical means to minimise light nuisance on site. Regard shall be had to the guidance detailed in the Institute of Lighting Professionals - Guidance Note 01/21 – Reduction of Obtrusive Light.
The CEMP to be submitted shall be in report format and as a minimum is to include the following details as specified in the subheadings below:
• Program and Phasing Details
o Site layout
o Operational hours
o Expected duration of demolition and construction work phases
• Site Management
o Contact details of site manager for public liaison purposes
o Complaints procedure - Roles and responsibilities
• Routes for Construction Traffic
o Routes to be used for access onto site and egress
o One way systems
o Haul routes (onsite and delivery)
• Site Access, Storage and Movement of Materials
o Delivery access point details
o Location details of storage areas, including parking of vehicles and areas for loading / unloading of materials
o Delivery times of materials and plant
• Dust, Debris and Mud
o Screening and hoarding
o Preventative measures
o Dust suppression measures
o General and machinery
o Wheel wash facilities
o Road sweeping facilities
o Covering of dusty stockpiles
o Vehicles carrying dusty loads
o Dust monitoring
o Boundary checks
o Monitoring of weather including wind speed and direction, dry conditions etc
• Noise and Vibration Control
o Silencing of vehicles, plant and machinery
o Mitigation measures for noisy operations
o Operational hours
o One way systems
o Vehicle reverse alarms
o Leaflet drops to noise sensitive premises
• Artificial Lighting
o Hours of operation of the lighting
o Location and specification of all of the luminaires
o Level of maintained average horizontal illuminance for the areas that needs to be illuminated
o Predicted vertical illuminance that will be caused by the proposed lighting when measured at windows of any properties in the vicinity
o Measures that will be taken to minimise or eliminate glare and stray light arising from the use of the lighting that is caused beyond the boundary of the site
• Waste Management
o Waste storage
o Waste collection
o Recycling
o Waste removal
Reason
To safeguard the amenities of the occupiers of nearby properties and promote sustainable development.
Highways
06
Before the development is commenced road sections, constructional and drainage details shall be submitted to and approved by the Local Planning Authority, and the approved details shall be implemented before the development is completed.
Reason
No details having been submitted they are reserved for approval.
Landscapes and Trees
07
No development within 6m of the river wall and existing habitat shall take place until a landscape and ecological management plan, including long-term design objectives, management responsibilities and maintenance schedules for all landscaped areas (except privately owned domestic gardens), has been submitted to, and approved in writing by, the local planning authority. The landscape and ecological management plan shall be carried out as approved and any subsequent variations shall be agreed in writing by the local planning authority.
The scheme shall include the following elements:
• Biodiversity Gain Plan and Habitat Management and Monitoring Plan, to secure the recommendations of the Biodiversity Net Gain Assessment
• details of maintenance regimes
• details of any new habitat created on-site
• details of treatment of site boundaries and/or buffers around water bodies
• details of a sensitive lighting scheme, avoiding unnecessary lighting of the watercourse and riparian zone
• details of management responsibilities
Reason
To ensure the protection of wildlife and supporting habitat. Also, to secure opportunities for enhancing the site’s nature conservation value in line with national planning policy.
08
No operations (including initial site clearance) shall commence on site in connection with development hereby approved until a suitable scheme (Arboricultural Method Statement) for the protection of existing trees and hedgerows has been submitted and its installation on site has been approved in writing by the Local Planning Authority.
All protection measures must fully detail each phase of the development process taking into account demolition/site clearance works, all construction works and hard and soft landscaping works. Details shall include the following:
• A schedule of tree works for all the retained trees specifying pruning and other remedial or preventative work, whether for physiological, hazard abatement, aesthetic or operational reasons. All tree works shall be carried out in accordance with BS 3998.
• Timing and phasing of works
• Site specific demolition and hard surface removal specifications
• Site specific construction specifications
• Level changes
• A Tree protection plan** in accordance with BS5837* detailing all methods of protection, including but not restricted to: locations of construction exclusion zones, root protection areas, fit for purpose fencing and ground protection, service routes, works access space, material/machinery/waste storage and permanent & temporary hard surfaces.
All tree protection methods detailed in the approved Arboricultural Method Statement shall not be moved or removed, temporarily or otherwise, until all works including external works have been completed and all equipment, machinery and surplus materials have been removed from the site, unless the prior approval of the Local Planning Authority has first been sought and obtained.
*Using the most recent revision the of the Standard
** Plans must be of a minimum scale of 1:200 (unless otherwise agreed by the Local Planning Authority)
Reason
To ensure appropriate tree protection in the interests of protecting the visual amenity of the area, contributing to the quality and character of Rotherham’s environment, air quality and adapting to and mitigating climate.
09
Notwithstanding the details submitted with this application, prior to construction works commencing above ground level, a detailed landscape scheme of soft landscaping shall be submitted to, and approved in writing by, the Local Planning Authority. The landscape scheme shall be prepared to a minimum scale of 1:200 and shall clearly identify through supplementary drawings where necessary:
• The extent of existing planting, including those trees or areas of vegetation that are to be retained, and those that it is proposed to remove.
• The extent of any changes to existing ground levels, where these are proposed.
• Any constraints in the form of existing or proposed site services, or visibility requirements.
• Areas of structural and ornamental planting that are to be carried out.
• The positions, design, materials and type of any boundary treatment to be erected.
• A planting plan and schedule detailing the proposed species, siting, quality and size specification, and planting distances.
• A written specification for ground preparation and soft landscape works.
• The programme for implementation.
• Written details of the responsibility for ongoing maintenance and a schedule of operations.
The scheme shall thereafter be implemented in accordance with the approved landscape scheme and in accordance with the appropriate standards and codes of practice within a timescale agreed, in writing, by the Local Planning Authority.
Reason
To ensure that there is a well laid out scheme of healthy trees and shrubs in the interests of amenity.
10
Any plants or trees which within a period of 5 years from completion of planting die, are removed or damaged, or that fail to thrive shall be replaced within the next planting season. Assessment of requirements for replacement planting shall be carried out on an annual basis in September of each year and any defective work or materials discovered shall be rectified before 31st December of that year.
Reason
To ensure that there is a well laid out scheme of healthy trees and shrubs in the interests of amenity.
Ecology
11
Notwithstanding the submitted details, before above ground construction works commence details of external / internal lighting shall be submitted to and approved in writing by the Local Planning Authority. The details shall clearly demonstrate that lighting will not cause excessive light pollution or disturb or prevent bats or other species using key corridors, foraging habitat features or accessing roost sites.
Reason
To minimise light pollution and reduce the impact on wildlife.
12
No removal of hedgerows, trees or shrubs, buildings or structure shall take place between 1st March and 31st August inclusive, unless a competent ecologist has undertaken a careful, detailed check of vegetation for active birds’ nests immediately before the vegetation is cleared and provided written confirmation that no birds will be harmed and/or that there are appropriate measures in place to protect nesting bird interest on site. Any such written confirmation should be submitted to the local planning authority.
Reason
In order not to disturb any bats or birds and to make adequate provision for species protected by the Wildlife & Countryside Act 1981.
13
No development shall take place (including demolition, ground works, vegetation clearance) until a Construction Environmental Management Plan (CEMP: Biodiversity) has been submitted to and approved in writing by the local planning authority.
The CEMP (Biodiversity) shall include the following.
a) Risk assessment of potentially damaging construction activities.
b) Identification of ‘biodiversity protection zones’.
c) Practical measures (both physical measures and sensitive working practices) to avoid or reduce impacts during construction (may be provided as a set of method statements).
d) The location and timing of sensitive works to avoid harm to biodiversity features.
e) The times during construction when specialist ecologists need to be present on site to oversee works.
f) Responsible persons and lines of communication.
g) The role and responsibilities on site of an ecological clerk of works (ECoW) or similarly competent person.
h) Use of protective fences, exclusion barriers and warning signs.
The approved CEMP shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details, unless otherwise agreed in writing by the local planning authority.
Reason
In the interests of biodiversity and ecology.
14
The development shall not commence until a Habitat Management and Monitoring Plan (HMMP) has been submitted prepared in accordance with the approved Biodiversity Gain Plan and including:
a) a non-technical summary;
b) the roles and responsibilities of the people or organisation(s) delivering the [HMMP];
c) the planned habitat creation and enhancement works to create or improve habitat to achieve the biodiversity net gain in accordance with the approved Biodiversity Gain Plan;
d) the management measures to maintain habitat in accordance with the approved Biodiversity Gain Plan for a period of 30 years from the completion of development; and
e) the monitoring methodology and frequency in respect of the created or enhanced habitat to be submitted to the local planning authority, has been submitted to, and approved in writing by, the local planning authority.
Reason
To secure the 30 year management and maintenance of the biodiversity net gain habitat creation.
Drainage and Flood Risk
15
The development shall be carried out in accordance with the submitted flood risk assessment (Titled ‘Flood Risk Assessment Site Address Riverside Quarter, Rotherham, S60 1BQ’ dated 06/09/2024 Complied by STM Environmental Consultants Limited) and the following mitigation measures it details:
• there shall be no ground level raising as outlined in section 14.2.1 (Finished Floor Levels) of the FRA; and
• the flood defence level of the flood walls shall not be reduced as result of the proposed development.
These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the scheme’s timing/phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development.
Reason
To reduce the risk of flooding to the proposed development and future occupants and to prevent flooding elsewhere by ensuring that compensatory storage of flood water is provided.
Canal and River Trust
16
Prior to the commencement of piling works on site, a detailed methodology for piling operations on site shall first be submitted to and approved in writing by the Local Planning Authority. Information within the methodology report shall contain:
• Details of vibration control and monitoring
• Details of permanent loading from the new piled structure and its impact on the existing retaining wall (including the provision of loading calculations from a competent person)
• Measures to protect the existing retaining wall next to the River Don during piling works
Thereafter, works will be carried out in accordance with the approved details.
Reason
In the interests of securing land stability on site.
Land Contamination
17
Prior to above ground works commencing, a limited Phase II Intrusive Site Investigation should be undertaken to assess potential geotechnical and geo-environmental conditions to confirm the nature, presence and extent of potential contamination within the northwestern section of the site and the risk it presents to human health/environment. The investigation and subsequent risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority.
The above works shall be conducted in line with guidance document ‘Land Contamination Risk Management’ (October 2020) and predecessor guidance ‘Model Procedures for the Management of Land Contamination, CLR 11 (Environment Agency, 2004) and BS10175:2011+A2 2017 (BSI, 2017).
Reason
To ensure the safe occupation of the site.
18
Prior to above ground works commencing and subject to the findings of condition 17 above, a Remediation Method Statement shall be provided and approved by this Local Authority prior to any remediation works commencing on site. The approved Remediation works shall be carried out in full on site under a quality assurance scheme to demonstrate compliance with the proposed methodology and best practice guidance. The Local Authority must be given two weeks written notification of commencement of the remediation scheme works.
Reason
To ensure the safe occupation of the site.
19
If during development works unexpected significant contamination is encountered, the local planning authority shall be notified in writing immediately. Any requirements for remedial works shall be submitted to and approved in writing by the Local Authority. Works thereafter shall be carried out in accordance with an approved Method Statement. This is to ensure the development will be suitable for use and that identified contamination will not present significant risks to human health or the environment.
Reason
To ensure the safe occupation of the site.
20
If subsoil/topsoil is required to be imported to site for remedial works/areas of soft landscaping, then these soils will need to be tested at a rate and frequency to be agreed with the Local Authority to ensure they are free from contamination.
Reason
To ensure the safe occupation of the site.
21
Following completion of any required remedial/ground preparation works a Verification Report should be forwarded to the Local Authority for review and comment. The Verification Report shall include details of the remediation works and quality assurance certificates to show that the works have been carried out in full accordance with the approved methodology. Details of any post-remedial sampling and analysis to show the site has reached the required clean-up criteria shall be included in the Verification Report together with the necessary documentation detailing what waste materials have been removed from the site. The site shall not be brought into use until such time as all verification data has been approved by the Local Authority.
Reason
To ensure the safe occupation of the site.
Informative(s)
01
Biodiversity Net Gain
Unless an exception or a transitional arrangement applies1, the effect of paragraph 13 of Schedule 7A to the Town and Country Planning Act 1990 is that planning permission granted for the development of land in England is deemed to have been granted subject to the condition “(the biodiversity gain condition”) that development may not begin unless:
(a) a Biodiversity Gain Plan has been submitted to the planning authority, and
(b) the planning authority has approved the plan.
The planning authority, for the purposes of determining whether to approve a Biodiversity Gain Plan in respect of this permission would be Rotherham MBC. Failure to submit a Biodiversity Gain Plan prior to the commencement of development will lead to formal enforcement action being considered, which could be in the form of a Temporary Stop Notice (that will require all development on site to stop, for a period of 56 days).
Biodiversity Gain Plan
The biodiversity gain plan must include/accompanied by:
(a) information about the steps taken or to be taken to minimise the adverse effect of the development on the biodiversity of the onsite habitat and any other habitat;
(b) the pre-development biodiversity value of the onsite habitat;
(c) the post-development biodiversity value of the onsite habitat;
(d) any registered offsite biodiversity gain allocated to the development and the biodiversity and the biodiversity value of that gain in relation to the development;
(e) any biodiversity credits purchased for the development;
(f) any information relating to irreplaceable habitat making up onsite habitat
(g) information about steps taken or to be taken to minimise any adverse effect of the development on, and arrangements for compensation for any impact the development has on the biodiversity of, any irreplaceable habitat4 present within the onsite baseline.
(h) any additional information requirements stipulated by the secretary of state.
The effect of section 73D of the Town and Country Planning Act 1990
If planning permission is granted on an application made under section 73 of the Town and Country Planning Act 1990 (application to develop land without compliance with conditions previously attached) and a Biodiversity Gain Plan was approved in relation to the previous planning permission (“the earlier Biodiversity Gain Plan”) there are circumstances when the earlier Biodiversity Gain Plan is regarded as approved for the purpose of discharging the biodiversity gain condition subject to which the section 73 planning permission is granted.
Those circumstances are that the conditions subject to which the section 73 permission is granted:
1. do not affect the post-development value of the onsite habitat as specified in the earlier Biodiversity Gain Plan, and
2. in the case of planning permission for a development where all or any part of the onsite habitat is irreplaceable habitat the conditions do not change the effect of the development on the biodiversity of that onsite habitat (including any arrangements made to compensate for any such effect) as specified in the earlier Biodiversity Gain Plan.
- Listed exemptions from Statutory BNG and transitional arrangements can be found at Biodiversity net gain: exempt developments - GOV.UK (www.gov.uk)
- The Statutory Biodiversity Gain Plan template can be found at https://www.gov.uk/government/publications/biodiversity-gain-plan
- Minimum legal requirements for the Biodiversity Gain plan can be found at https://www.legislation.gov.uk/ukpga/2021/30/schedule/14#:~:text=paragraph%2015).-,Biodiversity%20gain%20plan,-14
- Irreplaceable habitats for the purposed of Biodiversity Net Gain are defined by Biodiversity Gain Requirements (Irreplaceable Habitat) Regulations 2024. A full list of irreplaceable habitats can be found at https://www.legislation.gov.uk/uksi/2024/48/schedule/made
- Additional information required is outlined by Articles 37C(2) [Non Phased] 37C(4) [Phased] of The Town and Country Planning (Development Management Procedure) (England) Order 2015 and may be subject to the nature of your application https://www.legislation.gov.uk/uksi/2015/595#:~:text=Additional%20content%20of%20plan
- Where a Habitat Management and Monitoring Plan is required: https://publications.naturalengland.org.uk/publication/5813530037846016
02
You should note that the Council’s Neighbourhood Enforcement have a legal duty to investigate any complaints about noise or dust which may arise during the construction phase. If a statutory nuisance is found to exist they must serve an Abatement Notice under the Environmental Protection Act 1990. Failure to comply with the requirements of an Abatement Notice may result in a fine of up to £20,000 upon conviction in the Magistrates' Court. It is therefore recommended that you give serious consideration to reducing general disturbance by minimising dust and preventing mud, dust and other materials being deposited on the highway.
03
Nature conservation protection under UK and EU legislation is irrespective of the planning system and the applicant should therefore ensure that any activity undertaken, regardless of the need for any planning consent, complies with the appropriate wildlife legislation. If any protected species are found on the site then work should halt immediately and an appropriately qualified ecologist should be consulted. For definitive information primary legislative sources should be consulted.
Furthermore, vegetation removal should be undertaken outside of the bird breeding season, March to September inclusive. If any clearance work is to be carried out within this period, a nest search by a suitably qualified ecologist should be undertaken immediately preceding the works. If any active nests are present, work which may cause destruction of nests or, disturbance to the resident birds must cease until the young have fledged.
If a protected species (such as any bat, great crested newt, dormouse, badger, reptile, barn owl or any nesting bird) is discovered using a feature on site that would be affected by the development or related works all activity which might affect the species at the locality should cease. You should then seek the advice of a suitably qualified and experienced ecologist and consider the need for a licence from Natural England prior to commencing works (with regard to bats). This action is necessary to avoid possible prosecution and ensure compliance with the Wildlife & Countryside Act 1981 (as amended), the Conservation of Habitats and Species Regulations 2017 (as amended), the Protection of Badgers Act 1992 and the Wild Mammals Act 1996. This advice note should be passed on to any persons or contractors carrying out the development/works.
04
The applicant/developer is advised to contact the Trust’s Works Engineering Team via email at Enquiries.TPWNorth@canalrivertrust.org.uk or via switchboard on 0303 040 4040 in order to ensure that any necessary consents are obtained and that the works comply with the Canal & River Trust’s ‘Code of Practice for Works Affecting the Canal & River Trust’.
05
The Environment Agency would like to draw the applicants/ LPA’s attention to the following informative comments:
Missed opportunity for river restoration to support implementation of RMPBs.
Advice to LPA/applicant
In line with the Humber River Basin Management Plan (RBMP), we recommend that the proposed development is used as an opportunity to restore more natural processes to the watercourse and the associated riparian corridor. We would encourage applicants to consider opportunities for riparian habitat creation across the site. This would offer a significant environmental gain.
The Humber RBMP states that the water environment should be protected and enhanced to prevent deterioration and promote the recovery of water bodies. The riparian zone holds significant importance to our ecosystem.
The legally binding objectives of the RBMP detail the environmental improvements that are required to achieve the WFD objective of Good Ecological Status or, in the case of Artificial and Heavily Modified Water Bodies (HMWB), Good Ecological Potential – note, the Water Environment (WFD)(E&W) Regulations 2017 Part 6, paragraph 33 places a duty on each public body including local planning authorities to ‘have regard to’ RBMPs.
The river Don at this site is part of the WFD catchment Don from River Rother to River Dearne (GB104027057452), a HMWB. There are HMWB mitigation measures assigned to the water body that are required to be delivered in order to achieve WFD objectives.
The proposed development will take place within the riparian zone of this waterbody and should consider opportunities to restore loss of river and riparian habitat.
Environmental permit - advice to applicant
The Environmental Permitting (England and Wales) Regulations 2016 require a permit or exemption to be obtained for any activities which will take place:
• on or within 8 metres of a main river (16 metres if tidal)
• on or within 8 metres of a flood defence structure or culverted main river (16 metres if tidal)
• on or within 16 metres of a sea defence
• involving quarrying or excavation within 16 metres of any main river, flood defence (including a remote defence) or culvert
• on the floodplain of a main river if the activity could affect flood flow or storage and potential impacts are not controlled by a planning permission
For further guidance please visit https://www.gov.uk/guidance/flood-risk-activities-environmental-permits or contact our National Customer Contact Centre on 03708 506 506 (Monday to Friday, 8am to 6pm) or by emailing enquiries@environment-agency.gov.uk
The applicant should not assume that a permit will automatically be forthcoming once planning permission has been granted, and we advise them to consult with us at the earliest opportunity.
Signing up for flood warnings
The applicant/occupants should phone Floodline on 0345 988 1188 to register for a flood warning or visit https://www.gov.uk/sign-up-for-flood-warnings. It’s a free service that provides warnings of flooding from rivers, the sea and groundwater, direct by telephone, email or text message. Anyone can sign up.
Flood warnings can give people valuable time to prepare for flooding – time that allows them to move themselves, their families and precious items to safety. Flood warnings can also save lives and enable the emergency services to prepare and help communities.
For practical advice on preparing for a flood, visit https://www.gov.uk/prepare-for-flooding
To get help during a flood, visit https://www.gov.uk/help-during-flood
For advice on what do after a flood, visit https://www.gov.uk/after-flood
POSITIVE AND PROACTIVE STATEMENT
During the determination of the application, the Local Planning Authority worked with the applicant to consider what amendments were necessary to make the scheme acceptable. The applicant agreed to amend the scheme so that it was in accordance with the principles of the National Planning Policy Framework.
|