Conditions / Reason for Refusal: |
01
The proposed development fails to meet the Microgeneration Certification Scheme (MCS) criteria of 42dB and insufficient information has been submitted to enable the local planning authority to make a full assessment of the likely noise impacts of the proposed development on neighbouring properties. As such the proposed development is contrary to Policy SP52 ‘Pollution Control’.
Positive and Proactive Statement
The applicant did not enter into any pre application discussions with the Local Planning Authority. Whilst discussions during the determination of the application have identified a possible acceptable alternative to this proposal, the applicant has been unwilling to amend the scheme. This was not considered to be in accordance with the principles of the National Planning Policy Framework and resulted in this refusal.
|