Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications as shown on the approved plans (as set out below)
(Drawing No EDD ZZ ZZ DR A (00)03 A) received on 12th August 2024
Reason
To define the permission and for the avoidance of doubt.
03
All items of noise generating plant shall be positioned as shown in Figure 2 of the Noise Impact Assessment undertaken by Nova Acoustics, dated 25th July 2024 (Project No: NP-011188) provided in support of the application. provided in support of the application.
Reason
In the interests of amenity of neighbouring properties.
04
The Sound Power Level (LWA) of the air source heat pump shall not exceed those set out in Table 2 of the Noise Impact Assessment undertaken by Nova Acoustics, dated 25th July 2024 (Project No: NP-011188) provided in support of the application.
Reason
In the interests of neighbouring amenity
Positive and Proactive Statement
Whilst the applicant did not enter into any pre application discussions with the Local Planning Authority, the proposals were in accordance with the principles of the National Planning Policy Framework and did not require any alterations or modification.
|