Conditions / Reason for Refusal: |
Conditions
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
Positive and Proactive Statement
During the determination of the application, the Local Planning Authority worked with the applicant to consider what amendments were necessary to make the scheme acceptable. The applicant agreed to amend the scheme so that it was in accordance with the principles of the National Planning Policy Framework.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans (as set out below)
• (Drawing number 2022-120-003 Rev A) Nov 22
Reason
To define the permission and for the avoidance of doubt.
03
The materials to be used in the construction of the external surfaces of the development hereby permitted shall match those used in the existing building.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity.
04
The proposed balcony shall not be used until the screening shown on drawing 2022-120-003 Rev A has been fully installed. The screening shall be retained in perpetuity.
Reason
In the interest of preventing overlooking of neighbouring properties.
|