Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans (as set out below)
(Drawing number CS-DP-85-003 Rev 1, CS-DP-85-004 Rev 1, CS-DP-85-002 Rev 1, CS-DP-85-005 Rev 1, CS-DP-85-006 Rev 1 as received 16/06/2021 and CS-DP-85-001 Rev 3 as received 16/07/2021.)
Reason
To define the permission and for the avoidance of doubt.
03
The materials to be used in the construction of the external surfaces of the development hereby permitted shall match those in the approved plans.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity and in accordance with Core Strategy Policy CS28.
04
The materials to the front elevation of the dwellinghouse are to be brickwork to match the existing. Notwithstanding the submitted details, the front elevation is to be brick, and details of which are to be submitted and approved by the local authority
Reason
To create a standard of design and protect neighbouring amenity.
|