Conditions / Reason for Refusal: |
01
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications as shown on the approved plans (as set out below) except as shall be otherwise agreed in writing by the Local Planning Authority.
(Amended elevations, floor plans & site plan 02 Rev A) (Received 28 June 2021)
Reason
To define the permission and for the avoidance of doubt.
02
No above ground development shall take place until details of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted or samples of the materials have been left on site, and the details/samples have been approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details/samples.
Reason
To ensure that appropriate materials are used in the construction of the development in the interests of visual amenity.
03
Before the development is brought into use, that part of the site to be used by vehicles shall be constructed with either;
a/ a permeable surface and associated water retention/collection drainage, or;
b/ an impermeable surface with water collected and taken to a separately constructed water retention/discharge system within the site.
The area shall thereafter be maintained in a working condition.
Reason
To ensure that surface water can adequately be drained and that mud and other extraneous material is not deposited on the public highway and that each dwelling can be reached conveniently from the footway in the interests of the adequate drainage of the site, road safety and residential amenity.
Informative
01
Gigabit-capable full fibre broadband: The four South Yorkshire Authorities have committed to ensuring that relevant developments are provided with Gigabit-capable full fibre broadband. Please refer to the attached informative in this respect.
POSITIVE AND PROACTIVE STATEMENT
During the determination of the application, the Local Planning Authority worked with the applicant to consider what amendments were necessary to make the scheme acceptable. The applicant agreed to amend the scheme so that it was in accordance with the principles of the National Planning Policy Framework.
|