Conditions / Reason for Refusal: |
01
The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
Reason
In order to comply with the requirements of the Town and Country Planning Act 1990.
02
The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications and as shown on the approved plans (as set out below)
Drawing numbers 20_08-01, 20_089-02, 20_08-03 received 28 January 2021 and 20_08-04, 20_08-05, 20_08-06, 20_08-07, 20_08-08 received 25 February 2021.
Reason
To define the permission and for the avoidance of doubt.
03
The materials to be used in the construction of the external surfaces of the development hereby permitted shall match those used in the existing building.
Reason
In order to ensure a satisfactory appearance in the interests of visual amenity.
04
Before the development is brought into use, the proposed patio screen shown on plan no 20_08-05 shall be erected and shall thereafter be retained.
Reason
In the interests of the amenities of the occupiers of adjacent properties.
Informatives
01
Please note that there is an existing combined sewer which may be close to the extension. This sewer is the responsibility of Severn Trent Water. All permissions to connect, divert, or build over or adjacent to must be obtained from them before works commence on site.
Positive and Proactive Statement
During the determination of the application, the Local Planning Authority worked with the applicant to consider what amendments were necessary to make the scheme acceptable. The applicant agreed to amend the scheme so that it was in accordance with the principles of the National Planning Policy Framework.
|