Conditions / Reason for Refusal: |
01
[PC52] No development shall take place until samples of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the Local Planning Authority and the development shall be carried out in accordance with the approved details.
02
[PC97] The permission hereby granted shall relate to the area shown outlined in red on the approved site plan and the development shall only take place in accordance with the submitted details and specifications as shown on the approved plans (as set out below) except as shall be otherwise agreed in writing by the Local Planning Authority.
(Drawing 006/10)(received 17/02/10)
01
[PR52] To ensure that appropriate materials are used in the construction of the development in the interests of visual amenity and in accordance with UDP Policy ENV3.1 ‘Development and the Environment’.
02
[PR97] To define the permission and for the avoidance of doubt.
|